Thursday, 05 December 2019

Works in Torre Milano started succesfully less than a month ago and several basic construction jobs have been already executed or are undergoing.

In fact the concrete CFA poles (reducers of foundation subsidence) have been installed into the ground for a lenght of 13 meters and are  now being trimmed to allow the laying down of the main foundation platform.

The concrete basis of the two planned high cranes for the construction site are being carried out.