Live from the construction site
PROGRESS: 15%
expected availability: 2022
Wednesday, 29 July 2020
Look inside
Friday, 24 July 2020
Look inside
Wednesday, 01 July 2020
Yesterday, Tuesday 30 June 2020, the casting of the ground floor of the main body of Torre Milano took place.About 300 cubic meters of concrete...
Look inside
Tuesday, 26 May 2020
A fundamental milestone for Torre Milano: start of works for the groundfloor .Works started again last May the 4th in Torre Milano after the forced closing...
Look inside
Thursday, 27 February 2020
Works in Torre Milano proceed at full speed: the second underground floor has been completed and first underground is now being built.Soon ground floor will...
Look inside
Wednesday, 22 January 2020
Also the second one of the two cranes planned to be installed in the Torre Milano construction site has been mounted. Initially at an height of 64...
Look inside
Monday, 13 January 2020
Today was a fundamental day in Torre Milano as the major foundation was laid down.Works went on for the entire day with the contribution of about...
Look inside
Wednesday, 18 December 2019
The first out of the two cranes planned for the incoming works in Torre Milano was mounted yesterday December 17th .Enjoy here following some interesting  camera shots...